Q International handles
all the complexities of the sourcing process.
We work with you from design to delivery
so that purchasing and manufacturing overseas
becomes a simple and seamless process.
The Sourcing Timeline:
Receive product specification from client.
Locate right supplier and provide initial cost estimates
to client (5-15 days)
If client agrees to prices, provide sample (including design
consultation if needed) to
client (15-30 days)
If samples are to client’s specifications, sign and proceed
with production contract
(30-45 days)
Quality control management (5 days)
Shipping/Freight and Delivery to Customer (5-45 days)
Estimated total time
from concept to delivery: (60 -140 days or 2 to 4.5 months)